
Published: 22 March 2017
A town in northeast Thailand looks into the feasibility of a design-build-operate scheme for developing a controlled landfill site.
Overview
Like many municipalities in Asia, Mahasarakham town in the northeast region of Thailand faces the massive challenge of escalating volumes of solid waste along with deficient landfill infrastructure, technical skills, and regulation. While Mahasarakham does have formal and informal waste collection, the municipality’s landfill site runs as an uncontrolled dump posing significant threat to surface and groundwater.
The Asian Development Bank (ADB) provided technical assistance on mainstreaming solid waste management to Mahasarakham and four other cities in Asia. Key assistance was a review and upgrade of municipal 10-year plans for solid waste management plus one tailored project per city. Issues covered were waste avoidance, minimization, and recycling; waste haulage and disposal; and information, education and communication campaigns.
In Mahasarakham, after consulting stakeholders, the project team and the municipality developed and agreed on an enhanced integrated solid waste management plan. Due to strong interest from the municipality, the project team also conducted a pre-feasibility study into how the private sector could fill the technical gaps required for developing a controlled landfill site. A key element of the project was the series of meetings with private providers to gauge interest in in design, remediation, construction, and operation of a controlled landfill site through a public-private partnership.
Project information
Project snapshot
- April 2015: Project start
- March 2017: Project end
- US$ 1.4 million:Total cost of technical assistance over 2 years
- Financing
- Government of Thailand’s Pollution Control Department (PCD), Ministry of Natural Resources and Environment, Department of Energy, Ministry of Energy and Business, and Buriram Municipality: Stakeholders
Challenges
The landfill in Mahasarakham town operates as an uncontrolled dumpsite. Employees demonstrated low technical knowledge of how a controlled landfill site should operate. For example, the majority of the site had uncovered waste placed at very flat slopes, which generates landfill leachate and associated hazards. Leachate was observed flowing off the dumpsite perimeter onto neighboring properties.
More specifically, when developing cells at the site the operator has constructed a perimeter of earthen bund, which has the potential to form a large dam. At the time of inspection, in the dry season, it was already partially full with a large volume of landfill leachate.
The problem of leachate will be exacerbated if the approach to developing a series of enclosed bunds and then a plateau mound with a flat top continues even if suitable final cover is applied. Leachate will contaminate local surface waters with potential to pollute local groundwater reserves. There are also many areas where waste has been placed in an uncontrolled manner resulting in areas of exposed waste throughout the site.
While the current landfill design and operation are creating extensive environmental problems, discussions with operators and managers indicated that the city would not be able to run a controlled landfill to an appropriate standard without ongoing external support.
In addition, the city has a priority to minimize the quantity of residuals going to landfill. City officers expressed interest in converting waste to energy, particularly refuse derived fuel or RDF as a possible method of diverting waste. This is a process in which waste is separated and prepared to “RDF 2” quality then transported and sold to modern cement kiln owners that buy it as a coal substitute for the heating process.
Solutions
The pre-feasibility study confirmed that solid waste management challenges would be best addressed by a private contractor taking full control of operations and being compensated for construction, remediation as per agreed milestones, and for operations on the basis of fee per ton of new waste. There would be a deduction if the private operator failed to achieve specified performance targets. This ensures that a fixed price is agreed upon for construction and remediation costs and that there is year-to-year stability in the operating budget.
The study included a scope of works for a private contract, including design for the remediation of the existing dumpsite, accepting new waste on a daily basis, and design and development of a new controlled landfill. The remediation works would require the waste to be re-profiled, compacted, and covered with soil while it waits to be incorporated into the controlled landfill.
The controlled landfill design would involve the development of a suitably profiled valley formation for the first cell, complete with a suitable impermeable liner and incorporation of leachate collection drains. Leachate would then be directed to a pump station from which it would either be irrigated in dry weather or reinjected/stored during the wet weather periods.
The design would allow for the entire landfill site to eventually be integrated into one mound to maximize site airspace efficiency, as well as cost recovery efficiency for the capital works. It also has the added benefit of maximizing the incorporation of steep batter slopes on the site, thereby minimizing rain water infiltration and greatly reducing leachate generation rates.
Under the municipality’s 10-year integrated solid waste management plan, the city will complement the public-private partnership activities with extensive information, education, and communication campaigns to help reduce the amount of waste reaching the landfill.
Financial tables for Landfill Development and Operation
A: Capital Expenditure (CAPEX)
No. | Item | Unit | Quantity | Cost (US$) | THB (million) |
---|---|---|---|---|---|
CAPEX financed by the operator (excluded from the design-build-operate or DBO contract) | |||||
Landfill Operating Equipment | |||||
1 | Dozer (Caterpillar D6 or equivalent with landfill blade) | Item | 1 | 200,000 | |
2 | Excavator/ end Loader - assume Caterpillar D200 or equivalent | Item | 1 | 150,000 | |
3 | 10 wheeler tipping dump truck | Item | 1 | 70,000 | |
4 | 8,000L Water tank with pump | Item | 1 | 12,000 | |
TOTAL | 432,000 | 15.103 | |||
Sensitivity | 1 |
No. | Item | Unit | Value |
---|---|---|---|
1 | Equipment | Years depreciation | 7 |
2 | Civil works | Years depreciation | N/A |
3 | Annual depreciation equipment | US$ | 60,000 |
4 | Annual depreciation equipment | THB | N/A |
CAPEX included in the DBO contract | |||
5 | Total CAPEX in DBO contract | US$ | 1,006,130 |
6 | Total CAPEX in DBO contract | THB million | 35.174 |
7 | Years repayment DBO to operator | years | 2 |
8 | Annual payment DBO to operator | US$ | 569,627 |
9 | Annual payment DBO to operator | THB | 19.914 |
B: Operating Expenditure (OPEX)
Item | Description | Hours / day | Number | No. of days / year | Rate (US$) | Unit | Annual cost (US$) |
---|---|---|---|---|---|---|---|
General Manager (office based mainly) | 8 | 1 | 312 | 1,750.00 | month | 21,000 | |
Site Engineer (Part time) | 8 | 1 | 52 | 1,200.00 | month | 14,400 | |
Site Supervisor | 8 | 1 | 365 | 800.00 | month | 9,600 | |
Dozer Driver | 8 | 1 | 365 | 350.00 | month | 4,200 | |
Excavator Driver | 8 | 1 | 365 | 350.00 | month | 4,200 | |
Truck Driver | 8 | 1 | 365 | 300.00 | month | 3,600 | |
Gate keepers/clerk recording waste loads | 8 | 2 | 365 | 260.00 | month | 6,240 | |
General Hands | 8 | 8 | 365 | 260.00 | month | 24,960 | |
Dozer | Caterpillar D6 or equivalent | 6 | 1 | 312 | 25 | hour | 46,800 |
Excavator/Loader | Caterpillar 200 series or equivalent | 2 | 1 | 312 | 20 | hour | 12,480 |
Truck | Rigid body 6 X 4 10 wheel tipper | 2 | 1 | 312 | 20 | hour | 12,480 |
15 | |||||||
Dewatering pump for cell internal rain | 5L/s relocatable diesel motor sump pump | 24 | 1 | 40 | 2 | hour | 1,920 |
Leachate Pumps | 5kW electric motor driving a submersible progressive cavity pump | 4 | 1 | 365 | 2 | hour | 2,920 |
Cover soil | Assume 10% soil to waste volume on average | 4,140 | 12 | Cubic Metres | 49,680 | ||
Topographical Survey of landfill | Annual | 1 | Item | 5,000 | |||
Minor items and utilities | Allowance for general office power, water, phone and other minor items, such as signage | 1 | Item | 18,000 | |||
TOTAL | 237,480 |
C: Income statement
Income Statement (THB million) | Year | |||||
---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | ||
1 | Revenues | 33.924 | 34.777 | 14.863 | 15.309 | 15.768 |
1.1 | Annual O&M contract payment | 14.010 | 14.863 | 14.863 | 15.309 | 15.768 |
1.2 | DBO milestone payment | 19.914 | 19.914 | |||
2 | Operating expenditures | 13.701 | 14.112 | 14.112 | 14.536 | 14.972 |
2.1 | Total O&M | 13.701 | 14.112 | 14.112 | 14.536 | 14.972 |
3 | Operating Results (EBITDA) | 20.223 | 20.665 | 0.751 | 0.773 | 0.797 |
4 | Other costs | 1.970 | 0.985 | 0 | 0 | 0 |
4.1 | Depreciation equipment | 0 | 0 | 0 | 0 | 0 |
4.2 | Interest loan | 1.970 | 0.985 | 0 | 0 | 0 |
5 | Net profit/loss before corporate income tax | 18.25 | 19.68 | 0.75 | 0.77 | 0.80 |
6 | Corporate income tax | 4.56 | 4.92 | 0.19 | 0.19 | 0.20 |
7 | Net profit/loss after corporate income tax | 13.69 | 14.76 | 0.56 | 0.58 | 0.60 |
Results
Under the integrated solid waste management plan, Mahasarakham will enhance its waste minimization program through a range of IEC campaigns. These will include promoting the use of biodegradable bags and food containers and the 3Rs – reduce, reuse, recycle and segregating waste. The valuable segregated waste can then be sold.
The new plan allows for controlled scavenging at controlled landfills because this attains a high level of recycling efficiency.
The municipality will consider increasing waste collection and disposal fees along with proposed national legislation and apply the extra revenue to ongoing waste minimization campaigns.
The municipality will reduce food waste going to the landfill through the promotion of organic waste composting by households. This will significantly reduce wastes generated per day because food waste makes up a large fraction of municipal waste.
Lessons
Unrealistic marketing of refuse derived fuel
The sales and marketing teams of RDF companies were convincing municipalities in Thailand that refuse derived fuel is an economically feasible solution. The project team met with some of these companies to present the results of a pre-feasibility study from another project city, Buriram. The companies then admitted to the Mahasarakham officials that their proposal was not economically feasible under present conditions.
This approach of presenting quality data to marketing teams was very successful. It could be adopted in other cities to explain the realities of implementing refuse derived fuel and waste to energy projects.
Changes required to regulation of landfill design
The current landfill design requirements in Thailand limit the mound height to effectively four lifts or 10 to 12 meters. This greatly reduces site development efficiency in terms of airspace per unit area, and therefore increases the development costs and reduces landfill life. This approach also results in flat top landfills, which increases leachate generation rates that may lead to environmental issues.
The project team presented this issue to the most senior members of Thailand’s Pollution Control Department and recommended the restriction be removed to improve landfill life, cost efficiency, and minimize environmental impact.
Public-private partnerships to fill technical and skill gaps
The major lesson was that a public-private partnership would be the most effective way to improve landfill design, remediation, construction, and operation. The private sector would bring the essential skills and knowledge to improve landfill development. The municipal officers and the private sector operators supported this recommendation.
Resources
Asian Development Bank. 2017. Integrated Solid Waste Management for Local Governments: A Practical Guide. Mandaluyong City.
Asian Development Bank. Regional Capacity Development Technical Assistance on Mainstreaming Solid Waste Management in Asia
Prefeasibility Study on Landfill Upgrading Design Build Operate Contract: Mahasarakham, Thailand
Ask the Expert
Leave your question or comment in the section below:
YOU MIGHT ALSO LIKE
Disclaimer
The views expressed on this website are those of the authors and do not necessarily reflect the views and policies of the Asian Development Bank (ADB) or its Board of Governors or the governments they represent. ADB does not guarantee the accuracy of the data included in this publication and accepts no responsibility for any consequence of their use. By making any designation of or reference to a particular territory or geographic area, or by using the term “country” in this document, ADB does not intend to make any judgments as to the legal or other status of any territory or area.